Total Project Cost: PKR 93 Million
Barqaab Share 100%
Date of Commencement: January 2003
Date of Completion: January 2005
BARQAAB provided technical expert services in the Project for preparation of tender documents, estimates and contract evaluation. Construction Supervision of Syphonic Spillway, Lined Channel and related structures including falls, outfall structure and trash cleaning arrangements.
The proposed Spillway Project at Rasul Hydel Power Station lies on the Right Bank of Rasul Power Channel (RPC) adjacent to Rasul Power Station. It is about 11 KM north-east of Mandi Bahauddin and forms the central portion of the Chaj Doab lying between the Jhelum and Chenab rivers.
The Project comprises of the construction of spillway, having design discharge of 3,624 cusecs, design and construction of lined channel discharge capacity of 3,624 cusecs 2 Nos. Fall structure having the same discharge and fall is 16 ft., outfall structure, design of trash cleaning arrangements.