Total Project Cost: PKR 2,894 Million
Barqaab Share 100%
Date of Commencement: February 2005
Date of Completion: December 2008
Preparation of Layout Plans, Vetting of Estimates Technically and Financially, Inventory Control, Verification of Bill of Quantities, Quality Control, Construction Supervision, Progress Reports, Testing and Commissioning of the Projects for Villages to be electrified under Islamabad Electric Supply Company (IESCO) during the years from 2005 to December 2008.