Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document and Evaluation of the Bids.
Total Project Cost: PKR 284 Million and US$ 29.3 Million
Barqaab Share 100%
Date of Commencement: June 2003
Date of Completion: March 2004
Two Nos. 500/220kV 3x200MVA Transformer Bay
Two Nos. 220kV Line Bays
Two Nos. 500kV Line Bays
5KM 500kV Transmission Line
15KM 220kV Transmission Line