Preparation of Layout Plan, Single Line Diagram, Protection Schemes, Preliminary Civil Structure Design, Technical Specifications, Bill of Quantities and Tender Documents.
Total Project Cost: PKR 3,600 Million
Barqaab Share 100%
Date of Commencement: November 2008
Date of Completion: July 2009
3x160MVA, 220/132kV Transformer with Controlling Switchgear on both Sides
220kV D/C Transmission Line with Line Controlling Equipment for In/Out of one Circuit of Ravi-K.S.K Transmission Line at Shalamar (9KM Long
Overhead Transmission Line and 3+3KM underground Cable)
6.3MVA 13/211kV Transformer with Controlling Switchgear for Auxiliary Services.