500/220 kV GIS Gridstation alongwith 500kV IN/OUT and 220kV Transmission Line Feeding KESC Network – Residency Construction Supervision Including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, Follow Up and Revision Of Construction Schedules, Monitoring and Reporting Of Progress, Variation Orders and Design Changes During Execution, Testing And Commissioning, Final Completion Report And Handing Over The Project.
Total Project Cost: PKR 284 Million and US$ 29.3 Million
Barqaab Share 100%
Date of Commencement: October 2004
Date of Completion: December 2006
Two Nos. 500/220kV 3x200MVA Transformer Bay
Two Nos. 220kV Line Bays
Two Nos. 500kV Line Bays
5KM 500kV Transmission Line
15KM 220kV Transmission Line