Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost: PKR 713 Million
Barqaab Share 100%
Date of Commencement: January 2009
Date of Completion: June 2011
62KM long 220kV Double Circuit Twin bundle Transmission Line from 220kV Rohri Grid Station to 220kV Shikarpur Grid Station.
71KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Gambat Grid Station.
20KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Khairpur Grid Station.