Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost: PKR 2,500 Million
Barqaab Share 100%
Date of Commencement: January 2011
Date of Completion: June 2012
2x250MVA, 220/132kV ATFs.
2x220kV Dia.
6x132kV L/Bays.
1x10/13MVA, 132/11kV PTF
3x132kV T/Bays