Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost: RMB 55 Millions + PKR 365 Millions
Barqaab Share 100%
Date of Commencement: February 2010
Date of Completion: March 2012
Lot-I Kassowal 220 kV Grid Station:
Lot-II Two Twin Bundle, Double Circuit T/Lines for In & Out of Existing 220kV Vehari-Yousafwala D/C T/Line